A close-up of a city

AI-generated content may be incorrect.
A close-up of a letter

AI-generated content may be incorrect.
A close-up of a document

AI-generated content may be incorrect.
A close-up of a document

AI-generated content may be incorrect.
A close-up of a document

AI-generated content may be incorrect.
A close-up of a document

AI-generated content may be incorrect.


Contents

EXECUTIVE SUMMARY

Breaches of Action and Limit Levels for Air Quality  1

Breaches of Action and Limit Levels for Noise  1

Breaches of Action and Limit Levels for Water Quality  1

Environmental Complaints, Non-compliance & Summons  2

Reporting Change  2

Key Issues For The Next Three Months  2

1.    INTRODUCTION 

1.1   Background  3

1.2   Scope of the EM&A Report  4

1.3   Organisation Structure  4

1.4   Summary of Construction Works  5

1.5   Summary of EM&A Programme Requirements  6

1.6   Status of other Statutory Environmental Requirement  8

2.    MONITORING RESULTS 

2.1   Air Quality Monitoring  9

2.1.1    Monitoring Requirements and Equipment 9

2.1.2    Results and Observations  9

2.2   Noise Monitoring  11

2.2.1    Monitoring Requirements and Equipment 11

2.2.2    Monitoring Schedule for the Reporting Month  12

2.2.3    Results and Observations  12

2.3   Water Quality Monitoring  13

2.3.1    Monitoring Requirements and Equipment 13

2.3.2    Monitoring Schedule for the Reporting Month  15

2.3.3    Results and Observations  16

2.4   EM&A Site Inspection  16

2.5   Waste Management  18

2.6   Implementation Status of Environmental Mitigation Measures  20

2.7   Summary oF Complaints, Notification OF Summons AND Successful Prosecutions  20

3.    FUTURE KEY ISSUES 

3.1   Construction Programme for the coming Three Months  21

3.2   Monitoring Schedule for the Future 3 Months  22

4.    CONCLUSION AND RECOMMENDATIONS 

Annex A      PROJECT ORGANISATION

Annex B      Construction Programme

Annex C      Environmental Licenses and Permits of the Project

Annex D1    CALIBRATION CERTIFICATES (ONSITE SENSORS)

Annex D2    CALIBRATION CERTIFICATES (TRANSFER STANDARDS)

Annex D3    AIR QUALITY MONITORING RESULTS

Annex D4    WIND CONDITIONS

Annex D5    EVENT AND ACTION PLAN FOR AIR QUALITY MONITORING

Annex E1    Calibration Certificates (Sound Level Meters and Acoustic Calibrators)

Annex E2    Noise Monitoring Schedule during Reporting Period

Annex E3    Noise Monitoring Results

Annex E4    Event and Action Plan for Noise Monitoring

Annex F1     Calibration Certificates of Water Quality Monitoring Equipment

Annex F2     Water Quality Monitoring Schedule during Reporting Period

Annex F3     Water Quality Monitoring Results

Annex F4     Event and Action Plan for Water Quality Monitoring

Annex G      Waste Flow Table

Annex H      Environmental Mitigation Implementation Schedule

Annex I       Tentative Schedules of Environmental Monitoring for Future 3 Months

Annex J      Status of EP Submissions

 


 

LIST OF TABLES

Table 1.1     Summary of Environmental Permits under the Project and the Respective Active Works Contracts  3

Table 1.2     Contact Information of Key Personnel  4

Table 1.3     Major CONSRUCTION WORKS IN THE REPORTING PERIOD  5

Table 1.4     Summary of Status for the Environmental Aspects under the EM&A Manual  6

Table 2.1     Action and Limit Levels for Air Quality (Dust) 9

Table 2.2     Air Quality Monitoring Details  9

Table 2.3     Summary of 1-Hour RSP Monitoring Results in the Reporting Period  10

Table 2.4     Summary of 24-hour rolling average RSP Monitoring Results in the Reporting Period  10

Table 2.5     Summary of 24-hour rolling average FSP Monitoring Results in the Reporting Period  10

Table 2.6     Details of Exceedances Recorded for AIR Quality Monitoring  11

Table 2.7     Action and Limit Levels for Construction noise  11

Table 2.8     Noise Monitoring Details  12

Table 2.9     Summary of Construction Noise Monitoring Results in the Reporting Period  12

Table 2.10   Calculated Action and Limit Levels for Water Quality  13

Table 2.11   Locations of Impact Water Quality Monitoring Stations and Monitoring Requirements  14

Table 2.12   Water Quality Monitoring Equipment  15

Table 2.13   Details of Exceedances Recorded for Water Quality Monitoring  16

Table 2.14   Key Observations Identified during the site inspection in this Reporting Month  16

Table 2.15   Quantities of Waste Generated in Reporting Period  19

Table 3.1     Major Construction Works in the Next Three MOnths  21

 

LIST OF FIGURES

FIGURE 1.1    Location of Project

FIGURE 2.1    Locations of Air Quality Monitoring Stations

FIGURE 2.2    Locations of Noise Montioring Stations

FIGURE 2.3    Locations of Water Quality Monitoring Stations

 


Executive Summary

This is the Monthly Environmental Monitoring and Audit (EM&A) Report presenting the EM&A works during the period of October 2025 for the San Tin Technopole Phase 1 Development (the Project) in accordance with the EM&A Manual.  Two (2) works contracts, Package 1 Contract 1 (ND/2024/09) and Package 2 Contract 1 (ND/2024/10), are active in this reporting period.  

·        The construction of ND/2024/09 commenced on 29 September 2025; and

·        The construction of ND/2024/10 commenced on 18 September 2025.

A summary of EM&A activities conducted in the reporting period is listed below:

Air Quality Monitoring                             Continuous impact monitoring

Noise Monitoring

•      ND/2024/09                                     4 sessions

•      ND/2024/10                                     4 sessions

Water Quality Monitoring

•      ND/2024/09                                     13 sessions

•      ND/2024/10                                     13 sessions

Environmental Site Inspection

•      ND/2024/09                                     4 sessions

•      ND/2024/10                                     5 sessions

Environmental site audits, including weekly site inspections of construction works by representatives from ET, Engineer and Contractor; and joint site inspection with Independent Environmental Checker (IEC) were conducted during the reporting period.  Based on the audit results and the observation for the reporting period, environmental pollution control and mitigation measures for the Project were properly implemented.

Breaches of Action and Limit Levels for Air Quality

One (1) Action Level exceedance was recorded for impact air quality monitoring in the reporting period.  Relevant investigation and follow-up action were conducted according to the EM&A programme.  The exceedance was considered not related to the Project after investigation.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for impact noise monitoring in the reporting period. 

Breaches of Action and Limit Levels for Water Quality

Two (2) Limit Level exceedances were recorded for impact water quality monitoring in the reporting period.  Relevant investigations and follow-up actions were conducted according to the EM&A programme.  The exceedances were considered not related to the Project after investigation.

Environmental Complaints, Non-compliance & Summons

There was no environmental complaint, notification of summons or prosecution recorded in the reporting period.

Reporting Change

There was no reporting change in the reporting period.

Key Issues For The Next Three Months

Potential environmental impacts arising from the upcoming construction activities in the next three months are mainly associated with dust emission, noise from plant operation, handling and storage of C&D materials generated from construction activities, efficiency of wastewater and drainage management and tree protection.  The ET will keep track on the construction works to confirm compliance with environmental requirements and the proper implementation of all necessary mitigation measures. 


1.  Introduction

1.1     Background

San Tin Technopole Phase 1 Development (“the Project”) mainly covers innovation & technology (I&T) land parcels to the north of San Tin Highway/Fanling Highway, some residential land to the south and the key infrastructure areas with road connections. The construction of the Project will be delivered under various works contracts and its scope of works comprises the following elements:

•      Site formation of land for innovation and technology development, housing, community, commercial and other developments;

•      Engineering infrastructure works including but not limited to roadworks, drainage, sewerage, waterworks, pumping stations, fresh water and flushing water service reservoirs, Common Utility Tunnel (CUT) and other associated buildings / structures / E&M systems for the Project; and

•      Landscaping works;

The Environmental Impact Assessment (EIA) Report for the San Tin/Lok Ma Chau Development Node (STLMC DN) (Register No. AEIAR-261/2024) was approved on 17 May 2024. Two (2) works contracts, ND/2024/09 and ND/2024/10, are active in this reporting period.  The construction of ND/2024/09 commenced on 29 September 2025, and the construction of ND/2024/10 commenced on 18 September 2025. The location of the Project, including the associated works areas of each active works contract is shown in Figure 1.1. The relevant Environmental Permits (EPs) under the Project and the respective works contracts are summarized in Table 1.1.

 

Table 1.1  Summary of Environmental Permits under the Project and the Respective Active Works Contracts

EP

Designated Project

Work Contracts

ND/2024/09

ND/2024/10

EP-640/2024

San Tin / Lok Ma Chau Water Reclamation Plant

P

 

EP-641/2024

San Tin / Lok Ma Chau Effluent Polishing Plant

P

 

EP-664/2025

Revitalisation of San Tin Eastern Main Drainage Channel

 

 

EP-665/2025

Recreational Development (“Open Space”) along San Tin Western Main Drainage Channel and at Mai Po Lung Village within Deep Bay Buffer Zone 2

 

 

EP-666/2025

New Primary Distributor Road (Road P1) and District Distributor Roads (Roads D1, D2, D3, D4, D5 and D6) for San Tin / Lok Ma Chau Development Node

 

 


ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the Project in accordance with the requirements specified in the Environmental Permit(s), the Environmental Monitoring and Audit (EM&A) Manual, the EIA Report of the STLMC DN project and other relevant statutory requirements.

1.2     Scope of the EM&A Report

This is the Monthly EM&A Report for the Project which summarises the key findings of the EM&A programme during the reporting period of October 2025.

1.3     Organisation Structure

The organisation structure of the Project is shown in Annex A.  The key personnel contact names and details are summarised in Table 1.2 below.

 

Table 1.2  Contact Information of Key Personnel

Party

Position

Name

Telephone

Environmental Team (ET)

(ERM-Hong Kong, Limited)

ET Leader

Terence Fong

2271 3156

ET Leader Representative

(EP-640/2024)

Harris Wong

2271 3182

ET Leader Representative

(EP-641/2024)

Harmony Chuh

2271 3273

Independent Environmental Checker (IEC)

(Mott MacDonald Hong Kong Limited)

IEC

Thomas Chan

2828 5967

IEC Representative

(EP-640/2024)

Sunny Chan

2828 5962

IEC Representative

(EP-641/2024)

Jay Chua

2828 5710

Contract No. ND/2024/09

Civil Engineering and Development Department

Senior Engineer

Vicky W.K. Yuen

3426 2590

Engineer

Stanley C.Y. Hung

3152 3564

Engineer’s Representative

(ER)

(AECOM - Halcrow Joint Venture)

Chief Resident Engineer

Albert Yu

8493 0329

Senior Resident Engineer

Timonthy Chan

8494 6981

Senior Resident Engineer

Tony Chan

8491 4870

Contractor

(CR15G - Tung Lee Joint Venture)

Construction Manager

K. K. Yuen

9498 1213

Site Agent

Wilson Chan

9656 8865

Sub Agent

Paul So

5989 0614

Environmental Officer

Frank Liu

6900 3526

Environmental Supervisor

Johnny Kam

6178 4786

Contract No. ND/2024/10

Civil Engineering and Development Department

Senior Engineer

Albert S. Lam

3547 1635

Engineer

Patrick P.L. Wan

3152 3472

Engineer’s Representative

(ER)

(Arup - Binnies Joint Venture)

Senior Resident Engineer

Raymond Cheung

2908 4924

Contractor

(Kuly Construction &

Engineering Company Limited)

Senior Project Manager

Ma Kin Man

9552 1734

Site Agent

Tang Wing Kai

9300 7037

Environmental Officer

Brenda Yiu

9346 3966

 

1.4     Summary of Construction Works

As informed by the Contractor, details of the major construction works carried out in this reporting period are listed in Table 1.3.  The construction programme is shown in Annex B.

Table 1.3  Major CONSRUCTION WORKS IN THE REPORTING PERIOD

Construction Works Undertaken

Key Issues

Key Mitigation Measures

Contract No. ND/2024/09

•      Topographic Survey

•      Ground Investigation Work

•      Wetland Enhancement Works

•      Soldier Pile Wall Construction

•      Tree Felling

•      Demolition Works

•      Site Formation Works

•      Dust emission

•      Handling and storage of construction and demolition (C&D) materials

•      Noise from use of Powered Mechanical Equipment (PME)

•      Emission of dark smoke from PMEs

•      Proper discharge of wastewater

•      Prevention and proper discharge of surface runoff

•      Tree protection

•      Good site practices

•      Regular water spraying on stockpiles

•      Provide tarpaulin sheets coverage on stockpiles and reuse of C&D materials as far as practicable

•      Use of QPME and noise barrier/acoustic mat/enclosure

•      Regular maintenance of PMEs

•      Implementation of wastewater and drainage

management

•      Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

Contract No. ND/2024/10

•      Ground Investigation Work

•      Construction for Box Culvert

•      Tree Felling

•      Dust emission

•      Handling and storage of C&D materials

•      Noise from use of PME

•      Emission of dark smoke from PMEs

•      Proper discharge of wastewater

•      Prevention and proper discharge of surface runoff

•      Tree protection

•      Good site practices

•      Regular water spraying on stockpiles

•      Provide tarpaulin sheets coverage on stockpiles and reuse of C&D materials as far as practicable

•      Use of Quality Powered Mechanical Equipment (QPME) and noise barrier/acoustic mat/enclosure

•      Regular maintenance of PMEs

•      Implementation of wastewater and drainage

management

•      Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

1.5     Summary of EM&A Programme Requirements

The status for all environmental aspects is presented in Table 1.4.  The EM&A programme requirements remained unchanged during the reporting period.

Table 1.4  Summary of Status for the Environmental Aspects under the EM&A Manual

Parameters

Status

Air Quality

Impact Monitoring

On-going for Contract Nos. ND/2024/09 and ND/2024/10, monitoring conducted continuously

Noise

Baseline Monitoring

The results of baseline noise monitoring for Contract Nos. ND/2024/09 and ND/2024/10 were reported in Baseline Monitoring Report and submitted to EPD under the EM&A Manual Section 16.3 and EP Condition 3.3.

Impact Monitoring

On-going for Contract Nos. ND/2024/09 and ND/2024/10, monitoring conducted once per week

Water Quality

Baseline Monitoring

The results of baseline water quality monitoring for Contract Nos. ND/2024/09 and ND/2024/10 were reported in Baseline Monitoring Report and submitted to EPD under the EM&A Manual Section 16.3 and EP Condition 3.3.

Impact Monitoring

On-going for Contract Nos. ND/2024/09 and ND/2024/10, monitoring conducted 3 days per week

Waste Management

Waste Monitoring

On-going

Land Contamination

Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR)

On-going

Ecology

Wetland Compensation Monitoring

To be conducted when construction activities occur within 400m from the contiguous pond / wetland habitats on the northern portion of the Project area.

Night Roost Monitoring

Pre-construction Night Roost Survey commenced in September 2025 and on-going at the original roosting sites until commencement of tree felling works.

Upon the completion of re-provision of roosting substratum, night roost monitoring to be conducted monthly during dry season at the re-provision site.

Egretry Monitoring

To be conducted monthly during breeding season (between March and early September).

Flight Corridor Monitoring

To be conducted when construction activities occur within this flight corridor.

Woodland Compensation Monitoring

To be conducted after completion of compensatory planting.

Post-transplantation / Post-seedling Planting Monitoring of Flora Species of Conservation Importance

To be conducted after the transplantation / seedling planting.

Post-translocation Monitoring of Fauna Species of Conservation Importance

To be conducted after the translocation.

Pre-construction Site Check and Nest Control

To be conducted in breeding season (March to July). The associated nest control measures to be conducted in non-breeding season (August to February) after pre-construction survey.

Pre-construction Site Check for Eurasian Otter

To be conducted prior to the commencement of construction activities.

Wildlife Corridor Monitoring

To be conducted upon establishment of the wildlife corridors.

Site Environmental Audit

Regular Site Inspection

On-going

Environmental Log Book

On-going

 

Taking into account the construction works, impact monitoring of air quality, noise, water quality and waste management were carried out in the reporting period.  The monitoring schedule of noise and water quality are provided in Annex E2 and Annex F2 respectively.

The EM&A programme also involved environmental site inspections and related auditing conducted by the ET for checking the implementation of the required environmental mitigation measures recommended in the approved EIA Report and relevant EP submissions.  The relevant EP submissions are listed in Annex J.

1.6     Status of other Statutory Environmental Requirement

The environmental licenses and permits, including EP, discharge license under Water Pollution Control Ordinance, registration as chemical waste producer, construction noise permit and specified processes license, which were valid in the reporting period are presented in Annex C.  No non-compliance with environmental statutory requirements was recorded.

2.         Monitoring Results

2.1     Air Quality Monitoring

2.1.1  Monitoring Requirements and Equipment

According to the EM&A Manual of the Project, impact air quality monitoring in terms of 1-hour average Respirable Suspended Particulate (RSP), 24-hour rolling average RSP and 24-hour rolling average Fine Suspended Particulate (FSP) concentrations, was conducted continuously with air sensors.  The results of these monitoring parameters are compared with the corresponding Action and Limit levels listed in Table 2.1

Table 2.1  Action and Limit Levels for Air Quality (Dust)

Parameter

Action Level

Limit Level

1-hour RSP

150 μg/m3

Not applicable

24-hour RSP (rolling average)

Not applicable

100 μg/m3

24-hour FSP (rolling average)

Not applicable

50 μg/m3

 

The monitoring locations and air sensors used in the continuous impact air quality monitoring are summarised in Table 2.2 and illustrated in Figure 2.1.  Copies of the calibration certificates for the onsite air sensors at the monitoring stations and the transfer standards are presented in Annex D1 and Annex D2 respectively.

Table 2.2  Air Quality Monitoring Details

Monitoring Station

Relevancy to Works Contract

Location

Equipment

M03

ND/2024/10

Pun Uk Tsuen

MAS-Dust

(S/N: dev9204Z250700007)

M04

ND/2024/10

Chau Tau Tsuen

MAS-Dust

(S/N: dev9204Z250700006)

M06

ND/2024/09

Mai Po San Tsuen

MAS-Dust

(S/N: dev9204Z250800014)

M09

ND/2024/10

Wing Ping Tsuen

MAS-Dust

(S/N: dev9204Z250700005)

M11

ND/2024/09

Shek Wui Wai

MAS-Dust

(S/N: dev9204Z250800013)

M13

ND/2024/09

Rolling Hills (rooftop area)

MAS-Dust

(S/N: dev9204Z250800016)

M14

ND/2024/09

Rolling Hills (outside of Rolling Hills)

MAS-Dust

(S/N: dev9204Z250800015)

M15a (a)

ND/2024/09

The STEP

MAS-Dust

(S/N: dev9204Z250900019)

Note(s):

(a)   The permission from the property management office of M15a – The STEP has been granted within the reporting month.  The air quality monitoring at M15a commenced on 18 October 2025.

2.1.2  Results and Observations

The monitoring data and the graphical presentation for 1-hour RSP, 24-hour rolling average RSP and 24-hour rolling average FSP concentrations are summarised in Table 2.3 to

Table 2.5.  Major dust sources in the reporting period included haul road traffic and earth moving construction activities associated with the site formation works and tree felling works.  The monitoring data and the graphical presentation are provided in Annex D3.  Wind data during the reporting period extracted from the Hong Kong Observatory (HKO)’s weather station at Wetland Park are presented in Annex D4

Table 2.3  Summary of 1-Hour RSP Monitoring Results in the Reporting Period

Monitoring Station

Average (΅g/m3)

Range (΅g/m3)

Action Level (΅g/m3)

Limit Level (΅g/m3)

M03

13.4

3.4 - 35.2

150

Not applicable

M04

22.2

4.5 - 44.5

150

Not applicable

M06

28.5

4.1 - 63.0

150

Not applicable

M09

19.1

5.3 - 51.0

150

Not applicable

M11

28.9

6.1 - 168.6

150

Not applicable

M13

25.8

5.8 - 84.7

150

Not applicable

M14

22.0

5.0-57.1

150

Not applicable

M15a

30.7

5.8 - 73.1

150

Not applicable

 

Table 2.4  Summary of 24-hour rolling average RSP Monitoring Results in the Reporting Period

Monitoring Station

Average (΅g/m3)

Range (΅g/m3)

Action Level (΅g/m3)

Limit Level (΅g/m3)

M03

13.3

6.0 - 28.0

Not applicable

100

M04

22.1

8.6 - 34.2

Not applicable

100

M06

28.3

11.1 - 46.3

Not applicable

100

M09

19.0

8.1 - 36.6

Not applicable

100

M11

28.7

13.9 - 46.2

Not applicable

100

M13

25.6

10.8 - 43.0

Not applicable

100

M14

22.1

9.5 - 35.6

Not applicable

100

M15a

30.9

12.9 - 54.4

Not applicable

100

 

Table 2.5  Summary of 24-hour rolling average FSP Monitoring Results in the Reporting Period

Monitoring Station

Average (΅g/m3)

Range (΅g/m3)

Action Level (΅g/m3)

Limit Level (΅g/m3)

M03

8.7

3.2 - 20.2

Not applicable

50

M04

12.2

4.1 - 24.0

Not applicable

50

M06

11.9

3.9 - 23.2

Not applicable

50

M09

10.2

3.8 - 22.2

Not applicable

50

M11

12.1

5.1 - 26.1

Not applicable

50

M13

10.8

3.4 - 21.8

Not applicable

50

M14

10.7

3.1 - 21.9

Not applicable

50

M15a

13.5

3.7 - 25.8

Not applicable

50

 

One (1) Action Level exceedance was recorded for impact air quality monitoring in the reporting period.  Investigation on the exceedance was conducted and summarised in Table 2.6 below.  No Project-related exceedance was recorded after investigation.  No further action is therefore required to be undertaken in accordance with the Event and Action Plan presented in Annex D5.

Table 2.6     Details of Exceedances Recorded for AIR Quality Monitoring

Date

Monitoring Station

Parameter

Exceedance Level

No. of exceedance(s)

Time period

Remarks

21 October 2025

M11

1-hour RSP

Action Level

1

18:00-18:59

The exceedance was unlikely caused by the construction of the Project as no construction activity under ND/2024/09 was carried out and mitigation measures for air quality were implemented properly during the monitoring period.

 

2.2     Noise Monitoring

2.2.1  Monitoring Requirements and Equipment

According to the EM&A Manual of the Project, noise impact monitoring was conducted once per week during the construction phase of the Project.  The Action and Limit Levels for construction noise of the Project are provided in Table 2.7 below.

Table 2.7  Action and Limit Levels for Construction noise

Time Period

Action Level

Limit Level

0700 - 1900 hours on normal weekdays

When one documented complaint is received

75 dB(A)(a),(b)

Note:

(a)   If works are to be carried out during restricted hours, the conditions stipulated in the Construction Noise Permit (CNP) issued by the Noise Control Authority have to be followed.

(b)   70 dB(A) and 65 dB(A) for schools during normal teaching periods and school examination periods, respectively.

 

Noise monitoring was performed using sound level meter at the designated monitoring stations provided in Table 2.8 and Figure 2.2, in accordance with the requirements stipulated in the EM&A Manual.  Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.  Details of the deployed equipment are provided in Table 2.8.  Copies of the calibration certificates for the equipment are presented in Annex E1

Table 2.8  Noise Monitoring Details

Monitoring Station

Relevancy to Works Contract

Location

Parameter and Frequency

Monitoring Dates

Equipment

Type of Measurement

 

 

CM1

ND/2024/09

69 Mai Po San Tsuen

30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday)

Once per week for 30 mins during the construction period of the relevant works contracts of the Project

8, 14, 21 and 28 October 2025

Sound Level Meter: Rion NL-52 (S/N: 00331806)

 

Acoustic Calibrator: Larson Davis CAL200 (S/N: 11333)

Free field

CM3

ND/2024/09

Scenic Heights Block B2

Free field

CM4

ND/2024/09

30 Rolling Hills Phase II

Faηade

CM9

ND/2024/10

285B Wing Ping Tsuen

6, 13, 20 and 27 October 2025

Sound Level Meter: Rion NL-52 (S/N: 00542913)

 

Acoustic Calibrator: Larson Davis CAL200 (S/N: 11333)

Free field

CM10

ND/2024/10

291 Chau Tau Tsuen

Free field

CM11

ND/2024/10

218 Chau Tau Tsuen

Free field

2.2.2  Monitoring Schedule for the Reporting Month

The schedule for noise monitoring during the reporting period is provided in Annex E2.

2.2.3  Results and Observations

Results for noise monitoring are summarised in Table 2.9.  Major noise sources during the noise monitoring included noise from use of Powered Mechanical Equipment (PME) due to pile wall construction, tree felling, demolition and site formation works. The monitoring data and the graphical presentation are provided in Annex E3

Table 2.9  Summary of Construction Noise Monitoring Results in the Reporting Period

Monitoring Station

Average, dB(A),
Leq (30 min)

Range, dB(A),

Leq (30 min)

Limit Level, dB(A),

Leq (30 min)

CM1 (a)

69.6

68.6 – 70.6

75

CM3 (a)

53.3

49.3 – 54.8

75

CM4

47.0

41.7 – 50.2

75

CM9 (a)

64.7

64.1 – 65.4

75

CM10 (a)

57.7

54.2 – 60.4

75

CM11 (a)

53.2

52.5 – 54.4

75

Note(s):

(a)   A correction of +3 dB(A) was made to the free field measurements.

 

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period.  No action was thus required to be undertaken in accordance with the Event and Action Plan presented in Annex E4.

2.3     Water Quality Monitoring

2.3.1  Monitoring Requirements and Equipment

Water quality impact monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation if the deterioration of water quality is caused by the Project.  Impact water quality monitoring was undertaken three days per week during the reporting period in accordance with the EM&A Manual.  Each water quality impact monitoring was scheduled such that the interval between two water quality impact monitoring was more than 36 hours to record representative water quality data throughout the week.

Two (2) replicate in-situ measurements and samples were collected at each monitored water depth of each designated monitoring stations.  Dissolved Oxygen (DO), pH value, salinity, temperature and turbidity were measured in-situ whereas the level of suspended solids (SS) were determined by SGS Hong Kong Limited which is a HOKLAS accredited laboratory.

The calculated Action and Limit Levels of water quality monitoring with reference to the Baseline Water Quality Monitoring Report are provided in Table 2.10.

Table 2.10 Calculated Action and Limit Levels for Water Quality

Parameter

Action Level

Limit Level

San Tin Eastern Main Drainage Channel (STEMDC) - Station D1’

DO in mg/L (a)

1.2 mg/L

1.2 mg/L

SS in mg/L (b), (c)

105 mg/L, or 120% of upstream control station’s (U1a) SS recorded on the same day

113 mg/L, or 130% of upstream control station's (U1a) SS recorded on the same day

Turbidity in NTU (b), (c)

97 NTU, or 120% of upstream control station’s (U1a) turbidity recorded on the same day

102 NTU, or 130% of upstream control station's (U1a) turbidity recorded on the same day

San Tin Western Main Drainage Channel (STWMDC) - Stations D2a, D2b’, D2c and D2d

DO in mg/L (a)

1.3 mg/L

1.1 mg/L

SS in mg/L (b), 3

38 mg/L, or 120% of upstream control stations’ (U2a and U2b) SS recorded on the same day

46 mg/L, or 130% of upstream control stations’ (U2a and U2b) SS recorded on the same day

Turbidity in NTU (b), (c)

42 NTU, or 120% of upstream control stations’ (U2a and U2b) turbidity recorded on the same day

52 NTU, or 130% of upstream control stations’ (U2a and U2b) turbidity recorded on the same day

Small Watercourses along Sam Tam Road - Station D7

DO in mg/L (a)

0.6 mg/L

0.6 mg/L

SS in mg/L (b)

5 mg/L

5 mg/L

Turbidity in NTU (b)

11 NTU

12 NTU

Small Watercourses near Mai Po Village - Station D8

DO in mg/L (a)

1.4 mg/L

1.2 mg/L

SS in mg/L (b)

7 mg/L

8 mg/L

Turbidity in NTU (b)

12 NTU

13 NTU

Note(s):

(a)   For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

(b)   For SS and turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits

(c)   For clarity, the exceedance of Action / Limit Levels for SS and turbidity is considered to occur when both the baseline percentile criteria (based on 95%-ile / 99%-ile of collected baseline data) and control station criteria (based on 120% / 130% of control station data collected on the same day during impact monitoring) are exceeded. In case more than one upstream control station is involved, the higher number would be considered as the control criteria. Exceeding either the baseline percentile criteria or control station criteria alone does not constitute the exceedance of the corresponding Action / Limit Levels.

 

The locations of the monitoring stations under works contracts ND/2024/09 and ND/2024/10 are shown in Figure 2.3 and Table 2.11.

Table 2.11     Locations of Impact Water Quality Monitoring Stations and Monitoring Requirements

Monitoring Station

Relevancy to Works Contract

Coordinates

Description

 

Parameters and Frequency

Monitoring Dates

Easting

Northing

U1a

ND/2024/10

826721

838781

Upstream Station

In-situ measurements

•      DO (mg/L)

•      DO Saturation (%)

•      Salinity

•      Temperature ()

•      pH

•      Turbidity (NTU)

 

Laboratory measurements

•      SS (mg/L)

 

3 days per week during the construction period of the relevant works contracts of the Project.

2, 4, 6, 8, 10, 13, 15, 17, 20, 22, 24, 27 and 30 October 2025

U1b’ (a)

ND/2024/10

827146

840550

Upstream Station (Alternative Monitoring location of U1b)

G1a

ND/2024/10

826686

839212

Gradient Station

G1b

ND/2024/10

826472

839908

Gradient Station

G1c

ND/2024/10

826339

840303

Gradient Station

G1d

ND/2024/10

826316

840657

Gradient Station

D1’ (b)

ND/2024/10

825363

841421

Impact Station

U2a

ND/2024/09

826181

838334

Upstream Station

2, 4, 6, 8, 10, 14, 16, 18, 21, 23, 25, 27 and 30 October 2025

U2b’ (b)

ND/2024/09

825517

838767

Upstream Station (Alternative Monitoring location of U2b)

G2

ND/2024/09

825588

839518

Gradient Station

D2a

ND/2024/09

825200

839396

Impact Station

D2b’ (b)

ND/2024/09

824726

840168

Impact Station (Alternative Monitoring location of D2b)

D2c

ND/2024/09

824846

840373

Impact Station

D2d

ND/2024/09

825239

839846

Impact Station

D7

ND/2024/09

824254

838831

Impact Station

D8

ND/2024/09

824188

839310

Impact Station

Note(s):

(a)   Alternative water quality monitoring station U1b’ is used as fall-back option in case sampling at original monitoring station of U1b as per EM&A Manual is not practical due to low flow condition.

(b)   Alternative water quality monitoring stations D1’, D2b’ and U2b’ have been adopted as replacements of the original stations D1, D2b and U2b as per EM&A Manual due to access limitations.

 

The equipment used in the impact water quality monitoring work is summarised in Table 2.12 below.  Copies of the calibration certificates are attached in Annex F1.

Table 2.12     Water Quality Monitoring Equipment

Parameters (Unit)

Equipment

In-situ Measurement

Dissolved Oxygen (mg/L and % of saturation)

HORIBA U-50 Series U53 (S/N: FXMONLLF)

Salinity (ppt)

Temperature (°C)

pH

Turbidity (NTU)

Current Velocity (m/s)

雲境天合 LS300-B

Laboratory Analysis

Suspended Solids (SS) (mg/L)

Sample Container: 1L Clear Plastic Bottle

 

2.3.2  Monitoring Schedule for the Reporting Month

The schedule for water quality monitoring during the reporting period is provided in Annex F2.

2.3.3  Results and Observations

A total of twenty-six (26) monitoring events for impact water quality monitoring were conducted at all designated monitoring stations in the reporting period.  Impact water quality monitoring results and graphical presentations are provided in Annex F3

Two (2) Limit Level exceedances were recorded for impact water quality monitoring in the reporting period, including one (1) Limit Level for SS and one (1) Limit Level for Turbidity.  Investigations on the Limit Level exceedances were conducted and summarised in Table 2.13 below.

 

Table 2.13    Details of Exceedances Recorded for Water Quality Monitoring

Date

Monitoring Station

Parameter

Exceedance Level

Remarks

2 October 2025

D8

SS

Limit Level

The exceedances were unlikely caused by the construction of the Project as no construction activities that cause potential water quality impact were carried out near Station D8.

10 October 2025

D8

Turbidity

Limit Level

 

No Project-related exceedances were recorded after investigation.  No further action is therefore required to be undertaken in accordance with the Event and Action Plan presented in Annex F4.

2.4 EM&A Site Inspection

Site inspections were carried out on a weekly basis with the Contractor and ER to monitor the implementation of proper environmental pollution control and mitigation measures for air quality, noise, water quality, waste management, landscape and visual impacts under the Project.  In the reporting period, four (4) site inspections were carried out on 8, 14, 22 and 28 October 2025 for ND/2024/09, and five (5) site inspections were carried out on 2, 10, 16, 24 and 28 October 2025 for ND/2024/10.

Key observations during the site inspections are summarized in Table 2.14.

Table 2.14     Key Observations Identified during the site inspection in this Reporting Month

Inspection Date

Environmental Observations

Follow-up Status

ND/2024/09

8 October 2025

·        Designated area should be assigned for waste storage at Portion 1B.

·        Relevant EP should be displayed at all site entrances/exits.

·        Designated area has been assigned for waste storage at Portion 1B.

·        Relevant EP have been displayed at all site entrances/exits.

14 October 2025

·        Designated area should be assigned for waste disposal/storage at Portion 1D.

·        Drip tray should be placed under the oil container.

·        Designated area has been assigned for waste disposal/storage at Portion 1D.

·        Drip tray has been placed underneath the oil container.

22 October 2025

·        Relevant EP should be displayed at the site entrance/exit at San Tin Soccer Pitch.

·        The Relevant EP has been displayed at the site entrance and exit at San Tin Soccer Pitch.

28 October 2025

·        The Contractor was reminded to provide wheel washing facility at the site entrance, and to provide bunds to gully to direct runoff to designated treatment facility.

·        Wheel washing facility has been provided at the site entrance. Bunds to gully have been provided to direct runoff to designated treatment facility.

ND/2024/10

2 October 2025

•      No NRMM label was displayed for the excavator. The contractor was reminded to display NRMM label for the excavator.

•      Water spraying is not provided during breaking works. The contractor was reminded to provide water spraying for breaking works.

•      Noise acoustic wrapping is not provided for the breaker. The contractor was reminded to provide noise acoustic wrapping for the breaker to reduce noise emission from the breaking works.

•      NRMM label has been displayed for the excavator.

•      Water spraying has been provided during breaking works.

•      Noise acoustic wrapping has been provided for the breaker during breaking works.

10 October 2025

•      No particular observation.

•      The contractor was reminded that regular watering should be provided for exposed site surfaces and unpaved roads.

·        N/A

16 October 2025

•      Accumulation of stockpiles was observed on site. The Contractor was reminded to clear the stockpile regularly or provide coverings for the stockpile.

·        Stockpile was covered by tarpaulin sheet when idle.

24 October 2025

•      Breaking works without water spraying was observed on site. The Contractor was reminded to provide water spraying for breaking works.

·        Water spraying was applied during breaking works.

28 October 2025

•      Open stockpiles should be covered by tarpaulin sheet.

·        Stockpile was covered by tarpaulin sheet when idle.

2.5     Waste Management

Waste generated from the Works Contracts of the Project include inert construction and demolition (C&D) materials and non-inert C&D wastes. Sorting of C&D materials was carried out on site. Sufficient numbers of receptacles were available for general refuse collection and sorting.

Reference has been made to the waste flow tables prepared by the Contractors.  The quantities of different types of waste are summarised in Table 2.15.  Details of cumulative waste management data are presented as a waste flow table in Annex G.


Table 2.15    Quantities of Waste Generated in Reporting Period

Month

Contract No.

Inert C&D Materials (a) (b)

(m3)

Imported Fill (c) (m3)

Inert Construction Waste Reused (d) (m3)

Non-inert Construction Waste (e) (tonnes)

Recyclable Materials (f) (tonnes)

Chemical Waste (tonnes)

October 2025

ND/2024/09

0.00

0.00

0.00

5.00

0.003

0.00

ND/2024/10

0.00

0.00

0.00

35.73

0.000

0.00

Sub-total

0.00

0.00

0.00

40.73

0.003

0.00

Note:

(a)   Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill. 

(b)   The conversion factor for inert C&D Materials for ND/2024/10 is 2.4 tonnes/m3.

(c)   Imported materials from any source outside of the Project.

(d)   Reuse of inert construction waste generated under the Project.

(e)   Non-inert construction wastes include general refuse disposed at landfill.

(f)    Recyclable materials include metals, paper, cardboard, plastics and others.

 


 


2.6   Implementation Status of Environmental Mitigation Measures

A summary of the Environmental Mitigation Implementation Schedule is presented in Annex H.  The necessary mitigation measures were implemented properly for the Project.

2.7   Summary oF Complaints, Notification OF Summons AND Successful Prosecutions

There was no notification of summons or prosecution recorded in the reporting period.

3.         Future Key Issues

3.1     Construction Programme for the coming Three Months

Works to be undertaken in the next three months are summarised in Table 3.1 below, together with key issues and the key mitigation measures.

Table 3.1     Major Construction Works in the Next Three MOnths

Construction Works to be Undertaken

Key Issues

Key Mitigation Measures

Contract No. ND/2024/09

•      Topographic Survey

•      Ground Investigation Work

•      Wetland Enhancement Works

•      Soldier Pile Wall Construction

•      Tree Felling

•      Demolition Works

•      Site Formation Works

•      Dust emission

•      Handling and storage of C&D materials

•      Noise from use of PME

•      Emission of dark smoke from PMEs

•      Proper discharge of wastewater

•      Prevention and proper discharge of surface runoff

•      Tree protection

•      Good site practices

•      Regular water spraying on stockpiles

•      Provide tarpaulin sheets coverage on stockpiles and reuse of C&D materials as far as practicable

•      Use of QPME and noise barrier/acoustic mat/enclosure

•      Regular maintenance of PMEs

•      Implementation of wastewater and drainage

management

•      Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

Contract No. ND/2024/10

•      Ground Investigation Work

•      Construction for Box Culvert

•      Construction of Sewerage Pipe

•      Dust emission

•      Handling and storage of C&D materials

•      Noise from use of PME

•      Emission of dark smoke from PMEs

•      Proper discharge of wastewater

•      Prevention and proper discharge of surface runoff

•      Tree protection

•      Good site practices

•      Regular water spraying on stockpiles

•      Provide tarpaulin sheets coverage on stockpiles and reuse of C&D materials as far as practicable

•      Use of QPME and noise barrier/acoustic mat/enclosure

•      Regular maintenance of PMEs

•      Implementation of wastewater and drainage

management

•      Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works

 

The ET will keep track on the construction works to confirm compliance with environmental requirements and the proper implementation of all necessary mitigation measures.  The ET will also recommend to the Contractors about the environmental toolbox topics on the abovementioned key issues for the next reporting period.

3.2     Monitoring Schedule for the Future 3 Months

The tentative schedules for environmental monitoring in November, December 2025 and January 2026 are provided in Annex I.


 

4.         Conclusion and Recommendations

This EM&A Report presents the findings of the EM&A activities undertaken for the Project during the period of October 2025 in accordance with the EM&A Manual and the requirements of the EPs.  The environmental monitoring, site inspection, environmental complaint handling and EM&A reporting in works areas under Contract Nos. ND/2024/09 and ND/2024/10 were covered and carried out.

Air quality (1-hour RSP, 24-hour rolling average RSP and 24-hour rolling average FSP), noise and water quality monitoring were carried out in the reporting period.

One (1) Action Level exceedance was recorded for impact air quality monitoring in the reporting period.  Relevant investigation and follow-up action were conducted according to the EM&A programme.  The exceedance was considered not related to the Project after investigation.

The monitoring results for impact noise monitoring complied with the Action/ Limit levels in the reporting period.

Two (2) Limit Level exceedances were recorded for impact water quality monitoring in the reporting period.  Relevant investigations and follow-up actions were conducted according to the EM&A programme.  The exceedances were considered not related to the Project after investigation.

Environmental site inspections were carried out during the reporting period. 

Recommendations on remedial actions were given to the Contractors for the deficiencies identified during the site inspections.

There was no environmental complaint, notification of summons or prosecution recorded in the reporting period.

The ET will keep track on the construction works to confirm compliance with environmental requirements and the proper implementation of all necessary mitigation measures.